5MW anaerobic digestion plant

Imperial Park is a £26m development for AVG Power Ltd to construct a 5MW anaerobic digestion plant in Middlesbrough.

Location

  • Imperial Park, Middlesbrough

Sectors

Services

Sector:

Energy - BioConstruct GmbH

Services:

Applebridge Construction were employed to carry out all non-specialist M&E works including design of civils by the main contractor, German based M&E company BioConstruct GmbH.

Their challenge:

Extensive input was needed from an expert partner Like Applebridge to complete all non-specialist M&E works and various large reinforced concrete structures as well as sizable retaining walls and concrete slabs plus large tonnage steelworks.

Our solution:

The value of the works was approximately £5.1m and comprised a large reception hall, CHP building, 15-tank bases of varying, fit-out of the clean rooms and laboratories, extensive piling and ground remediation. Scope of works included:
  • 5MW anaerobic digestion plant
  • All non M&E including design works comprising:
    • Extensive piling and ground remediation (1500nr, 16m deep precast concrete piles)
    • Steel framed building (1000m2 GFA)
    • Large reinforced concrete structures
    • 1200m2 retaining walls
    • 500m3 concrete slabs
    • 400t steel
    • 400m of concrete retaining walls - 4.5m high
  • EPC form of contract

The results:

This £5.1m project commenced in December 2015 and was successfully completed a year later in December 2016.

Find Us

Hughes House
Cargo Fleet Road
Middlesbrough
TS3 6AG

Sat Nav TS3 6AF

Contact Us

01642 233400
info@applebridge.com

Office Opening Hours
Monday - Friday 08:00 - 17:30

Get in Touch

Our Family