Costain is delivering the A1 Birtley to Coalhouse improvement scheme, which includes widening the A1 and replacing a bridge structure over the East Coast Mainline. To progress this major upgrade, the Allerdene Burn watercourse needed to be safely diverted, all within a severely restricted working area bordered by the live railway, the A1 embankment and the existing burn. Strict temporary works requirements and a tight 24-week programme added further complexity.
Costain is delivering the A1 Birtley to Coalhouse improvement scheme, which includes widening the A1 and replacing a bridge structure over the East Coast Mainline. To progress this major upgrade, the Allerdene Burn watercourse needed to be safely diverted, all within a severely restricted working area bordered by the live railway, the A1 embankment and the existing burn. Strict temporary works requirements and a tight 24-week programme added further complexity.
OUR SOLUTION
Applebridge provided an integrated delivery model, utilising expertise from across the Applebridge Family to undertake earthworks, drainage, civils and reinforced concrete works. Early engagement allowed us to collaboratively develop practical design solutions that addressed the site constraints. This included using height-restricted machinery beneath the bridge and implementing extensive temporary works to allow multiple trades to operate safely.
SCOPE OF WORKS
Applebridge was appointed to complete the following packages of works:
Culvert diversion
Reinforced concrete works
Sheet-pile wing walls
Underground drainage
Concrete channels and troughs
Fall-prevention fencing
Earthworks
Grouting of previous culvert
THE RESULTS
Applebridge sucessfully completed the works ahead of programme, supporting the successful delivery of one of the most technically challenging elements of the A1 upgrade.
TESTIMONIAL
“Being able to draw on different parts of the Applebridge business to deliver a complex package of works has been extremely beneficial. The project team from Applebridge have been a collaborative team to work with and have delivered the works to a high standard.”David Lynn, Costain Project Director
VIDEO
We catch up with Project Director Paul Troubridge to learn more about Costain's Allerdene Beck project