Sector:
Education - Kier Construction
Services:
Construction of a new build two storey secondary school and a new build hospital mental health (autism) unit.
Their challenge:
The new builds needed on each site presented a unique set of parameters to work within, including being adjacent to either a working school environment or an operational mental health hospital environment.
Our solution:
Scope of works included:
- St Michael’s School, Billingham, £1.5m
- New build two storey secondary school
- All civils works inclusive of cut and fill, foundations, floor slab, drainage attenuation and externals including tarmacadam
- Bespoke JCT contract - remeasurable
- Works carried out adjacent to a live school environment
- Laurence Jackson Secondary School, Guisborough, £2.5m
- New build hospital (mental health unit)
- All works inclusive of cut and fill, foundations, floor slab inclusive of extensive retaining wall details, drainage and externals including tarmacadam
- NEC contract - lump sum
- Works carried out within a live mental health hospital environment
- Adjacent to significant live natural water course
The results:
This £4m project commenced in December 2014 and was successfully completed in November 2016.